Sheet index · Folio 2026 · Rev. 2026.10

  • A-000Cover
  • A-050Plates
  • A-100Drawing register
  • A-200Leadership ledger
  • A-300Legend
  • A-400Career
  • A-500About
  • A-600Studio
  • A-700Contact
  • A-101Building a design team for four Shopify apps
  • A-102One merchant experience across four Built-for-Shopify apps
  • A-103Virtual care that works for patients, caregivers and clinicians
  • A-104One token system, three product teams
  • A-105Mobile checkout and merchant tools
  • A-106From buildings to products
  • CopyCopy email
  • ViewSwitch theme
  • ViewMore contrast
  • ViewMotion off
  • GShow grid

From buildings to products

Six years taking residential and mixed-use buildings from concept to construction documents. The habits I lead with started there: circulation first, one grid, coordination before drawing.

Drawing sheet: Level 1 plan of a five-storey mixed-use building and Section A–A, set out on one 8.4 m grid. (open full size)

Impact

  1. Concept to construction documents

    Concept to construction documents: 11 projects, 2011–17

    Residential and mixed-use, 2011–17

  2. Consultant disciplines coordinated

    Consultant disciplines coordinated: up to 12, per project

    Per project, through weekly clash reviews

  3. Site RFIs per project

    Site RFIs per project: −30%, 2016 vs 2014

    2016 against 2014, after weekly coordination reviews

General notes7-minute sheet

The 60-second version

  1. Our own site teams built from every sheet, so every drawing clash became our own delay and cost.
  2. I learned to draw circulation first, set out one grid and coordinate a dozen disciplines before drawing.
  3. Weekly clash reviews cut site RFIs 30%; we cut an atrium to hold the cost plan.
  4. Most of how I run design teams started here.

Challenge

Existing conditions

“Which of these two drawings do I build from?” was the question our superintendent asked us every week.

The practice designed and built five-storey mixed-use buildings: retail at grade, suites above, a parkade below and up to twelve consultant disciplines on each job. Consultants met each other’s clashes on site, and most requests for information (RFIs) traced back to two drawings that disagreed: a duct through a beam, a door into a column.

Scope of work

My role

I led…

  • Worked on 11 residential and mixed-use projects from concept to construction documents, leading the later ones as project architect
  • Ran weekly clash reviews with up to 12 consultant disciplines and our site superintendents
  • Wrote the practice’s sheet-set standard: series, title block, keynotes and revision log
  • Took options and cost trade-offs to clients in person, before the estimate forced them
  • Reviewed junior architects’ sets sheet by sheet and coached them through their first construction documents

The team…

  • Project designers and technologists drew the sets with me, four to nine per project
  • A project manager owned the fee, the schedule and the client contract
  • Structural, mechanical, electrical, civil, code and cost consultants owned their own drawings
  • Our site teams built from the drawings and sent an RFI every time two of them disagreed
  • 1 × Project architect (me)
  • 6 × Project designers & technologists
  • 1 × Project manager
  • 1 × Contract administrator
  • 12 × Consultant disciplines

Constraints

What we had to work within

  • Zoning: height, setbacks, density and parking ratios
  • Building code: fire separations, exits and accessibility
  • A fixed cost plan, checked at every stage
  • Up to 12 consultant disciplines on one set
  • Design and construction under one roof: our own site teams built from every sheet

Principles

What we held to

  1. P1

    Circulation first.

    Before rooms, I drew how people move: street to lift, lift to suite, suite to exit, truck to loading bay. Rooms fill the space between.

  2. P2

    The grid is a promise.

    Set out the structural grid first and keep it. Every consultant, trade and future tenant plans against it, so moving one column moves everyone.

  3. P3

    Coordinate before you draw.

    An hour at one table with the structural and mechanical engineers saves a week of RFIs on site. Clashes are cheapest on paper.

Decision log

Decisions

D1Shipped
Decision

Weekly clash reviews with every consultant

Why
Most RFIs on our early projects traced back to two drawings that disagreed. A clash found on site cost a week; found on a Tuesday, it cost an hour.
Trade-off
Two hours a week from every consultant through design development and construction documents, time their fees had not planned for.
Risk watched
Reviews drifting into status meetings. Each one ended with a clash log: item, owner, due date, open or closed.
Owner
Me, with the project manager and each consultant’s lead
D2Shipped
Decision

One sheet-set standard for the practice

Why
Every team numbered, titled and noted its sheets differently. Consultants and our own site teams relearned the set on every job, and checking took longer than drawing.
Trade-off
A month of evenings rebuilding templates, and senior colleagues giving up habits they liked.
Risk watched
A standard nobody used. I piloted it on one project, then made it the template every new project opened from.
Owner
Me, with the practice’s principals
D3Status: Descoped
Decision

A double-height atrium over the residential lobby

Why
The pre-tender estimate came in 6% over the cost plan, and the atrium was most of it: two suites lost on Level 2, a fire separation and smoke control.
Trade-off
The lobby lost its tallest moment. A 3 × 6 m light well through the four residential floors brought daylight down to the lobby and into every corridor instead.
Risk watched
Dark corridors on the upper floors. We checked daylight on the section at every level before the client signed off.
Owner
Me, with the project manager, the cost consultant and the client
D4Shipped
Decision

One 8.4 m structural grid from the parkade to the roof

Why
8.4 m holds three parking stalls below, a shopfront at grade and a suite width above, so every column runs straight to the foundation without a transfer slab.
Trade-off
Suites had to fit the bay. Two corner suites took three rounds of planning before they worked.
Risk watched
Retail tenants wanting other frontages. The grid allowed shopfronts one or two bays wide, and we showed both to the leasing agent early.
Owner
Me, with the structural engineer

Plan

Draw the paths, then the rooms

On every plan I started with movement: street to lift, lift to suite, suite to exit, truck to loading bay. Rooms are what is left between the paths.

On this Level 1 the street doors, the mailboxes and both lifts sit on one straight line, 15 m long, and the three shops back onto a shared service corridor. It is the same instinct I now bring to user flows.

Level 1 plan at 1:100: street doors, mailboxes and both lifts on one straight line, with door tags and a room schedule. (open full size)
Fig. 01 P1 · Circulation first: street doors to lifts in one straight line, under the skylight; the shops back onto one service corridor.

Section

Cut the atrium, keep the light

The client loved the double-height lobby. The pre-tender estimate came in 6% over the cost plan, and the atrium was most of it.

Instead of defending the image, I went back to what it was for: daylight in the lobby and a sense of arrival. A 3 × 6 m light well through the residential floors did both, gave back the Level 2 suites the atrium had taken, and lit every corridor on the way down.

Section A–A from the parkade to the roof at +18.00, with a light well bringing daylight to a skylight over the lobby. (open full size)
Fig. 02 D3The light well runs from the roof to a skylight over the lobby, past every corridor on the way down.

Coordination

Clashes are cheapest on paper

From 2015 I ran a two-hour clash review every Tuesday: structural, mechanical, electrical and, once a job reached site, our superintendent, around one model and one printed set. Every clash went into a log with an owner and a date.

RFIs fell as projects drawn under the reviews reached site: 50 per project a quarter in 2014, 35 in 2016. It is the habit behind every design review I run with engineering today.

Site RFIs per project, by quarter
View as table
LabelValue (RFIs per project)Note
Q1 ’1448
Q253
Q347
Q452
Q1 ’1549Weekly clash reviews start
Q244
Q340
Q437
Q1 ’1636
Q234
Q335
Q435

Average RFIs per project under construction, by quarter. Projects drawn under the reviews reached site through 2015; 2016 is the first full year.

Fig. 03 D150 RFIs per project a quarter in 2014, 35 in 2016: −30%.

Drawing set

One standard for every sheet

Each team numbered and noted its drawings its own way, so consultants and our site teams relearned every set. I wrote one standard for the practice: sheet series, a single title block, keynotes tied to one legend, and revision clouds with a log entry for every change.

It is how I still think about a design system: agree the structure once, so people spend their time on the work. It is also why every page of this site is a numbered sheet.

One sheet-set standard
SeriesHoldsRule
A-000General: cover, sheet index, code analysisEvery set opens with the same index
A-100Plans, one per levelSame grid, same north, same origin
A-200ElevationsMaterials keyed to one legend
A-300SectionsLevels measured from ±0.00
A-500DetailsCalled up from plans and sections, never orphaned
A-600SchedulesDoors, windows and finishes keyed by tag

The practice standard: series numbers and the one rule each series keeps.

Fig. 04 D2Every set the practice issued from 2015 opened from this template.

Before / after

One 8.4 m structural grid from the parkade to the roof

Compare by
The Level 1 structural grid isolated: 8.4 m bays and 35 columns, with twelve layout columns overlaid in blue.Building grid, 2016
The same grid with an App Home laid on twelve columns: metric cards and panels break on the structural lines.Product grid, 2026
Fig. 05 D4Same frame, same lines: one 8.4 m bay holds two layout columns, and every panel breaks on a structural line.

Outcomes

After launch

  1. Launch

    2017

  2. +3 months

    6 series, 1 title block

    The sheet-set standard becomes the template every new project opens from

  3. +12 months

    Clash logs closed before tender

    The first projects drawn under weekly clash reviews reach site

  4. +2 years

    Site RFIs −30%

    RFIs per project settle at 35 a quarter, down from 50

Learnings

Revisions

Paths not taken

  1. Defend the atrium and cut finishes everywhere else to pay for it. The building would have looked right in renderings and worse to live in.
  2. Automated clash detection on its own. The model found the clashes; the Tuesday table got them owned and closed.
  3. A different grid for parking, shops and suites, joined by a transfer slab. More freedom on each floor, a deeper and costlier structure, and a building that fought itself.

Two reflections

  1. The drawing is not the building, and a design file is not the product. The work is getting everyone who builds it to read it the same way.
  2. The hardest conversations were about cost, not form. Taking a trade-off to a client early, with options and numbers, is still how I talk to leadership.

Go deeper

Details

Detail 1How a clash review ran

Every Tuesday, two hours, one table: me as project architect, the structural, mechanical and electrical engineers, and our site superintendent once construction started. Other disciplines joined when their drawings were in play.

We worked from one federated model and one printed set. Every clash went into a log with an owner, a due date and the sheets it touched; nothing left the room without a name on it.

The open items were the first page of the next week’s agenda, so they were the first thing everyone saw.

Detail 2The sheet-set standard

Six series: A-000 general, A-100 plans, A-200 elevations, A-300 sections, A-500 details and A-600 schedules. One title block with the consultant list and a revision table, keynotes tied to a single legend, and a revision cloud, a delta and a log entry for every change.

New projects opened from a template with the standard already in place, so following it was the easy path.

Detail 3What carried over to product design

Circulation became user flows. The structural grid became a layout grid and tokens. Clash reviews became design reviews with engineering. The cost plan became scope and sequencing. The drawing set became a design system.

Different vocabulary, same job: read the site, set out the grid, keep people moving, check the work.

Continue the set

Next sheets

Let’s talk about your product